Estimate concrete volume for slabs, footings, pads, and other rectangular placements.

Parameter sketch

Slab dimensions

Labels update with the current input values so the formula symbols stay tied to the geometry.

L = 20W = 12T = 6Use consistent length units; thickness is inches for US or mm for metric.Waste = 10%
L: 20W: 12T: 6Waste: 10%

Result

4.89 yd3 (3.74 m3) recommended order quantity

Base volume

120

Waste factor

10%

Cubic feet

132

Cubic yards

4.89

Cubic meters

3.74

Step-by-step calculation

  1. Convert thickness to feet: 0.5.
  2. Compute base volume: 20 x 12 x 0.5 = 120.
  3. Apply 10% waste factor: 120 x 1.1 = 132.

What this means

Use this as a preliminary quantity estimate and confirm ordering increments with the ready-mix supplier.

Formula Used

Volume = length x width x thickness

Step-by-Step Example

A 20 ft by 12 ft slab with 6 in thickness and 10% waste needs about 4.89 cubic yards.

Engineering Notes

Check units, assumptions, boundary conditions, groundwater, drainage, and whether the simplified method is appropriate before using a result in any project decision.

FAQ

Should I include waste?

Yes. Small jobs commonly use 5% to 10%; irregular excavations may need more.

Does this replace supplier takeoff?

No. Confirm delivery increments and site access with your supplier.